TORQUE is flexible in regards to how it can be upgraded. In most cases, a TORQUE "shutdown" followed by a configure, make, make install procedure as documented in this guide is all that is required (see Installing TORQUE). This process will preserve existing configuration and in most cases, existing workload.
A few considerations are included below:
- If upgrading from OpenPBS, PBSPro, or TORQUE 1.0.3 or earlier, queued jobs whether active or idle will be lost. In such situations, job queues should be completely drained of all jobs.
- If not using the pbs_mom -r or -p flag (see Command-line arguments), running jobs may be lost. In such cases, running jobs should be allowed to be completed or should be requeued before upgrading TORQUE.
- pbs_mom and pbs_server daemons of differing versions may be run together. However, not all combinations have been tested and unexpected failures may occur.
- When upgrading from early versions of TORQUE (pre-4.0) and Moab, you may encounter a problem where Moab core files are regularly created in /opt/moab. This can be caused by old TORQUE library files used by Moab that try to authorize with the old TORQUE pbs_iff authorization daemon. You can resolve the problem by removing the old version library files from /usr/local/lib.
To upgrade
- Build new release (do not install).
- Stop all TORQUE daemons (see qterm and momctl -s).
- Install new TORQUE (use make install).
- Start all TORQUE daemons.
Rolling upgrade
The enablemomrestart option causes a MOM to check if its binary has been updated and will restart itself at a safe point when no jobs are running, making upgrades easier. This can be enabled in the MOM config file, but it is recommended to enable it with momctl.
- Prepare the new version MOM package.
- Install the MOM package on the compute nodes.
- Run momctl -q enablemomrestart=1 -h :ALL.